The North Shore Levee will construct a 6.2 mile levee across the two cities, providing critical flood protection and removing over 3,100 properties from FEMA's mapped Special Flood Hazard Area. The project will build resiliency in the face of future flood events, retaining existing businesses, jobs, and residents which have been on the decline in the community. The total construction cost of the North Shore is estimated to be at least $78 million...Aberdeen - North Shore Levee Project (wa.gov)
• Planning (2015-2021) Collected traffic data, reviewed plans, gathered community input to the North Shore Levee.
• Design (2022 -2025) Conducted community outreach and collected feedback, are currently working to secure regulatory approval (e.g. Environmental Assessment) and developing increasingly detailed designs that reflect community and stakeholder feedback. Other Elements being worked on: Internal drainage hydraulic modeling updates, and right-of- way coordination.
• Construction (2027 – 2029): Dependent upon the timing of the completion of the FEMA Environmental Review We plan to construct the project and keep the community informed on the construction updates, schedules and expected impacts.
Questions?
Brian Shay
Nick Bird
nbird@aberdeenwa.gov
360-537-3218
Recently Completed Elements:
FEMA Open House – November 2023
Preliminary preferred alignment provided to FEMA – April 2024
Next Steps:
FEMA Environmental Review
FEMA Draft Environmental Assessment– Summer 2025